Three new housing and community schemes are being built on Salisbury Plain to accommodate service personnel relocating from Germany. Taylor Lane Timber Frame has supplied and erected 450 timber frame kits at the Bulford and Larkhill sites. The Hereford-based business is one of two timber frame manufacturers appointed by main contractor, Lovell.
The Defence Infrastructure Organisation has tasked Lovell with delivering 917 homes (Service Families’ Accommodation (SFA)) over three sites in a little over two years.
Taylor Lane Timber Frame and Stewart Milne Timber Systems were selected following rigorous qualitative scrutiny from a panel of the country’s leading manufacturers/installers.
Taylor Lane was charged with completing 225 units at Bulford and Stewart Milne, 242 units at Ludgershall. But Larkhill is different, comprising 450 units, twice the size of the other two.
The companies worked with six basic house types, to streamline manufacturing and build efficiencies. Taylor Lane used its 140mm timber frame system with 75mm insulation to achieve the required U-value (0.21 W/m2K). Each property is designed to have an energy performance 19% greater than Building Regulations requirements.
Taylor Lane kicked off by erecting 225 plots at Bulford, in just 29 weeks. This site set the standard for Taylor Lane, in both production output and operations. The company handed over the final frame at Bulford on 30th November 2018. Work had already started at the Larkhill site.
Larkhill required dedicated onsite management and efficient programming. Its success has been reliant on exceptional communication. The Taylor Lane and Stewart Milne site offices were opposite one another, for example, with the site supervisors meeting daily to share crane plans; road closures; deliveries and delivery schedules, to accommodate one other and not compromise the slew radius.
Initially, both companies handed over five units per week, this accelerated to a combined 16 units per week. This could not have been achieved with traditional masonry construction, the programme would have taken around five rather than two years to complete. This fast-track, high-volume project is an industry exemplar, demonstrating the benefits of timber frame for speed, precision and efficiency.
Taylor Lane celebrated the erection of its final unit at Larkhill; the last property of the contract, with a topping out ceremony on Friday 2nd August 2019.
With the final phase of the Army Basing Programme underway, military personnel have already begun the relocation to Salisbury Plain, occupying completed properties at Bulford and Ludgershall. Lovell is on track to complete the project in advance of the May 2020 deadline.